Our SAMT Rebar teams have just accomplished a remarkable feat on the Delta Junction HS2 site. As the A11 abutment footing of the River Tame West viaduct was very critical to the overall site schedule, our customer asked us to deploy major resources to lay the footing reinforcement as quickly as possible. The 330 tonnes of reinforcement were laid and delivered in 12 days of intensive work, with 2 shifts working 7 days a week.
The challenge was met! A big well done to our teams.
(Client: Joint venture BBV: Balfour Beatty Vinci)